Frontiers Quantifying the Underlying Causes of a Discrepancy Between Predicted and Measured Energy Use

Frontiers Quantifying the Underlying Causes of a Discrepancy Between Predicted and Measured Energy Use

In addition, typical lighting and equipment baseloads under compliance modeling are a gross under-prediction of actual baseloads measured in the four case study buildings. In Figure 8, energy end-uses for 3,000 simulations are compared with measured energy use (orange circles), displaying the uncertainty for each end-use. The carbon savings predictions that form the basis of this performance gap assessment for corridor lighting, are calculated using Eq. The metrics for assessing the use of corridor lighting in practice against project carbon and electricity saving estimates provides insights that could also be used in other mechanical and electrical installations in buildings, not just lighting. EB is CvD's academic supervisor during his doctoral studies and has reviewed the paper and provided feedback on the work, including direct insights from his own work. This paper highlights that a stronger emphasis on the use of performance modeling is needed, in order to drive design decisions that will effectively mitigate the risk of the energy performance gap.

A higher level of data granularity and availability of evidence can filter out inaccurate predictions. Occupancy, lights, and equipment schedules for the calibrated model compared with NCM (in black) assumptions for CH. The percentage impact on total energy use for each simplification is shown in Table 4. To determine the impact of regulatory assumptions on energy use predictions and consequently the performance gap, typical NCM assumptions (i.e., simplifications) were applied to the manually calibrated base case models.

The occupancy in the three corridor data collection areas is shown alongside the predicted value of operational hours in Figure 5, from the three areas a median value of 831 per annum, and SD of 354 (h/annum) are calculated. The predicted annual CO2e emissions and electricity consumption are compared with the measured values using the before and after process in Table 2 and is shown in Figure 4. Operational hours are used as a proxy for occupancy hours which is in turn used as a proxy for lights on hours. The heuristics, or rules of thumb, used in the assumptions could be perceived as overoptimistic in their major underestimation of the actual patterns of lights on hours which are 138% higher than predicted operational hours. The energy efficiency predictions for electricity consumption and reduction in CO2 equivalent emissions for the three buildings are detailed in Table 2. The designs and calculations used in these projects were carried out in 2012 and 2013, since then the LENI calculation has been further refined, for differentiating daytime, night time, and parasitic consumption, nonetheless the original calculation is used for comparison purposes.

The corridor locations—which are outside of classrooms—were specifically chosen to represent corridor spaces outside classrooms which are not solely occupied by one school or department but can be centrally booked by any group booking. For the period considered, the closure dates were 24 December–3 January and over the Easter period, including Maundy Thursday through to Easter Monday. All three buildings had corridor lighting assessments from the university’s external consultants, in house project managers, and sustainability team.

For reporting the the article itself performance gap in percentage terms, following the convention of other performance gap researchers (Bordass et al., 2001; Menezes et al., 2012; van Dronkelaar et al., 2016), the final comparison of predictions vs. actual data are displayed in Figure 13. The heuristics, or rules of thumb, used by the external consultants in the predicted operational hours have a large variability and error compared with actual measured values. The predicted operational hours, measured lights on hours, and measured occupancy hours across all three buildings are plotted in Figure 12.

Percentage impact of simplifications on total energy use compared to the calibrated model. Furthermore, the ASHRAE calibration criteria are for total energy use, and do not take into account the differences between energy end-uses. Statistical calibration criteria, differences between predicted and measured energy use.

This paper quantifies the impact of underlying causes of the regulatory energy performance gap in four case study buildings. The use of the HOBO™ loggers in lighting applications enables commissioning engineers to reduce the performance gap between the lights on hours of use and occupancy patterns. Using environmental loggers can provide an additional tool to support decision making in energy efficiency projects. However, as envisaged the Urban 2 location had a higher footfall from students due to the classrooms on the second floor and was almost 800 h in addition to those predicted in the original calculations. Maths 1 has been calculated using overestimates of operating hours both before and after the upgrade. The actual patterns of lights on hours after the corridor lighting retrofit are 67% lower than predicted operational hours.

All four case study buildings were calibrated within the ASHRAE criteria at a monthly level as shown in Table 2. These limitations are a common issue with model calibration, however, most could be alleviated through rigorous and continuous commissioning, in addition to ensuring that a reliable metering strategy is in place. Spearman correlation coefficients of input parameters on total energy use per building.

Spearman's rank correlation coefficient (SRCC) was calculated to assess the relationship between the inputs and outputs. Uncertainty analysis is typically accompanied by sensitivity analysis, which apportions the uncertainty of the model output to the input. A higher number of simulations increase the accuracy of the calculated correlations between inputs and outputs from sensitivity analysis. For each building, several thousand simulations were run in order to analyse the variance in predictions. All building spaces were included in the model and zoning of the spaces was identified during walk-throughs of the buildings.